When translated into a project network, a work package will become
A. A critical path.
B. A single activity.
C. An arrow.
D. One or more activities.
E. A milestone.
Answer: D
You might also like to view...
Which of the following situation would be appropriate for a value creating tactic or strategy?
A. a zero-sum situation B. a distributive situation C. a situation where there can be only one winner D. a non-zero-sum situation
Which of the six key sources of Big Data is being used when a company collects Big Data on customers in order to sell it to other organizations?
A. data from mobile apps B. data from business systems C. data from commercial entities D. data from government agencies E. data from Internet-connected devices
Which of the following syndication forms pays taxes?
A)?REITs B)?Partnerships C)?Subchapter S corporations D)?Limited liability companies E)?None of the above
If the activity level increases, then one would expect the fixed cost per unit to increase as well.
Answer the following statement true (T) or false (F)