The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

A. Slowly rise.
B. Drop sharply and then level out.
C. Remain about the same.
D. Rise sharply and then level out.
E. Slowly drop.


Answer: A

Business

You might also like to view...

During what part of the writing process does the writer ensure the accuracy of the information?

A) Defining the purpose B) Developing an audience profile C) Gathering the information D) Uncovering the audience's needs E) Providing required information

Business

A team typically handles decision making using the following methods except:

a. Consultative b. Authoritarian c. Democratic d. Consensus e. Directive

Business

Alfarsi Industries uses the net present value method to make investment decisions and requires a 15% annual return on all investments. The company is considering two different investments. Each require an initial investment of $15,000 and will produce cash flows as follows: End ofYearInvestment?AB1$8,000 $0 2 8,000  0 3 8,000  24,000   The present value factors of $1 each year at 15% are:  10.869620.756130.6575  The present value of an annuity of $1 for 3 years at 15% is 2.2832.The net present value of Investment A is:

A. $18,266. B. $3,266. C. $(15,000). D. $(20,549). E. $9,000.

Business

Arnold Palmer Hospital uses which focus?

A) process B) repetitive C) product D) mass customization E) A and D

Business