The intent of project oversight includes all of the following EXCEPT

A. Meet the needs of the organization through continuous improvement.
B. Support the project manager.
C. Meet the needs of the organization through procedures.
D. Meet the needs of the organization through accountability.
E. Meet the needs of the organization through improving everyday business activities.


Answer: E

Business

You might also like to view...

Risk reduction in and of itself is rarely a viable way to create shareholder value.

Answer the following statement true (T) or false (F)

Business

Answer the following statements true (T) or false (F)

APB Statement No. 4 acknowledges a conflict between the relevance and reliability objectives.

Business

Stress is always negative.

Answer the following statement true (T) or false (F)

Business

The Immigration and Naturalization Service (INS) was enlarged and made into a Cabinet-level agency with the passage of the Patriot Act in 2002

Indicate whether the statement is true or false

Business