How is a no damages for delay clause used during construction?

What will be an ideal response?


Typical notice provisions found in most construction contracts require that notice of the occurrence of a delay be provided within a fairly short period of time. Federal contracts require this notice within ten days and the standard American Institute of Architects contract forms require it to be within twenty days (Bramble and Callahan, 1987).

Trades & Technology

You might also like to view...

?After the surface of an aluminum AWS SENSE workmanship sample has been cleaned, it should be welded within ____ minutes.

A. ?10 B. 20? C. ?1 hour D. ?8 hours

Trades & Technology

____ involves the profession of planning, design, installation and maintenance of living plants

a. Horticultural management c. Interior design b. Plant retailing d. Professional interiorscaping

Trades & Technology

What is the alternative when public sewers are not available?

What will be an ideal response?

Trades & Technology

How many Btus are required to change one pound of ice at 20°F to steam at 220°F?

A. 1,304 Btu/h B. 2,608 Btu/h C. 6,520 Btu/h D. 3,912 Btu/h

Trades & Technology