Which of the following statements regarding CPM networks is true?

A) There can be multiple critical paths on the same project, all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths, all of them will have the same duration.
E) None of the above are true.


D

Business

You might also like to view...

A method that combines market-based pricing with a cost reduction emphasis is termed ________

a. product costing b. cost plus pricing c. theory of constraints d. target costing

Business

Key financial ratios that could help analysts measure Whole Foods' profitability do not include

A. inventory turnover. B. operating profit margin. C. return on capital employed. D. net return on assets. E. return on stockholders' equity.

Business

What is an application form? Describe how a candidate can be prepared to complete the form

What will be an ideal response?

Business

Expectancy theory includes the following events, in order:

A. outcome valence, performance, and effort B. performance, outcome valence, and effort C. effort, performance, and outcome valence D. performance, effort, and outcome valence E. effort, outcome valence, and performance

Business