The crash time of an activity represents
A) the normal time to complete an activity.
B) the most pessimistic time to complete an activity.
C) the incremental decrease in the time to complete an activity.
D) the shortened activity time.
E) None of the above
D
You might also like to view...
Carl, Anne, and Al were friends in college. After graduation they decided to open a computer
consulting business. They each have $20,000 to put into the business, and want equal shares of the business. However, they are worried about liability because they had heard of a consultant who crashed a client's computer and was sued for $1,000,000. They also want to avoid double taxation. The most likely form of business organization for them would be a A) corporation. B) partnership. C) limited partnership. D) sole proprietorship. E) Subchapter S corporation.
Litigants not satisfied with the decision of a court of limited jurisdiction may:
a. appeal to a superior court within the area b. request review by an administrative tribunal c. request a new trial at a court of general jurisdiction d. engage in a "certified refusal" of the verdict e. none of the other choices are correct
Human resource management of small firms should be identical to large companies but adjusted for size.
Answer the following statement true (T) or false (F)
Which of the following lists investment strategies in order from lowest risk to highest risk?
A) investing for growth < buying and holding < market timing < investing for income < value investing B) buying and holding < investing for income < investing for growth < value investing < market timing C) value investing < investing for income < investing for growth < market timing < buying and holding D) buying and holding < investing for growth < investing for income < value investing < market timing E) investing for income < buying and holding < value investing < investing for growth < market timing