You should work on this activity during lab hours.
(a) Develop a CPM network and determine the critical path for the events defined in the Gantt chart in Figure 2.1.
(b) Develop a Gantt chart for the events defined in Table 2.2.
(c) For the events defined in Table 2.5,
i. Complete the table.
ii. Draw the PERT network.
iii. Determine the probability of finishing the task on time if the design due date is later than 95 days.
a.
b.
c.