A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project

Activity Average Worst-Case
A 14 21
B 20 28
C 16 22
D 8 15
E 9 18
F 11 18
A) 44 days
B) 6 days
C) 17 days
D) 9 days


D

Business

You might also like to view...

Logistics includes the increasingly complex management of processes, information, and communication to take a product from cradle to grave. Cradle to grave provides logistics support.

Answer the following statement true (T) or false (F)

Business

As an OSHA compliance officer, after presenting his credentials to the operating manager at RioFit, Marv can hold private interviews with any of the firm's employees.

Answer the following statement true (T) or false (F)

Business

Most contracts are made ____________________

Fill in the blank(s) with correct word

Business

One who transfers rights under a contract is

a. the assignor. b. the assignee. c. the obligor. d. none of these.

Business