The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000. The crash time for this activity is 3 weeks and is expected to cost $32,000. The cost slope for Activity X is calculated as ______.
A. (32,000 – 12,000)/(5 – 3)
B. (12,000 – 32,000)/(5 – 3)
C. (32,000 – 12,000)/(3 – 5)
D. (12,000 – 32,000)/(3 – 5)
A. (32,000 – 12,000)/(5 – 3)
You might also like to view...
When respondents are unable to articulate a response to a question, this usually indicates they have no opinion on that topic
Indicate whether the statement is true or false
Which of the following statements is true of the European Union (EU)?
A) All issues have to be passed unanimously by the EU members to be enforced. B) Every country in the European Union has adopted the euro as its monetary unit. C) Custom duties have been removed among member nations of the European Union. D) Custom tariffs have been removed for trade between the EU and the rest of the world.
The Treaty Establishing the European Community and the ________ of 2010 are the principal sources of law in the EU, pertaining to business between and among its member states
A. Multilateral Agreement on Investment B. Lisbon Treaty C. Trade and Investment Framework Agreement D. Free Trade Agreement
Relationships with former colleagues will change after a member of the team is promoted to team leader.
a. True b. False