An opening in a tilt-up wall panel represents area of weakness during lifting and erecting operation, particularly if the opening extends close to the panel end. What measure is taken to ensure that such a panel does not crack or is otherwise damaged during lifting and erection?

What will be an ideal response?


A vertical steel wide -flange or channel section, called a strongback, is temporarily anchored to the panel segment
near the opening before lifting it. After the panel is in place, the strongback is removed.

Trades & Technology

You might also like to view...

________ can result in forage yield loss if basal leaves senesce.

A. Undergrazing B. Overgrazing C. Harvesting hay too early D. Harvesting silage too early

Trades & Technology

A P0122 DTC is retrieved using a scan tool. This DTC means ________

A) The TP sensor voltage is low
B) The TP sensor signal circuit could be shorted to ground
C) The TP sensor could be shorted to ground
D) All of the above are correct.

Trades & Technology

The address register generates the sequence of memory addresses from which program instructions are taken

Indicate whether the statement is true or false

Trades & Technology

Nail whitener are available in forms of cream, coating string, and paste, is applied:

What will be an ideal response?

Trades & Technology