Coordination on th job between contractors is neccessary to complete the job _______.

A. on time
B. on budget
C. as designed
D. satisfactorily


Answer: D

Trades & Technology

You might also like to view...

When preparing a progress report, focus on the status of the project and any ____________________ the team has encountered.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

Which if the following are the two most significant components of Light Loss Factor (LLF)? Select all that apply.

A) Temperature factor. B) Lamp lumen depreciation factor. C) Luminaire dirt depreciation factor. D) Lamp burnout factor.

Trades & Technology

Describe and give another name for standard parts.

What will be an ideal response?

Trades & Technology

The output of an OR gate is connected directly to the input of an AND gate. The other AND gate input is a constant "Enable" HIGH. A technician checks the inputs to the OR gate and notes a HIGH and LOW. The output of the OR gate is noted as being a HIGH. The "Enable" HIGH input to the AND gate is verified as normal. The technician checks the OR gate input to the AND gate and observes a LOW or no

voltage condition. Of the probable causes listed, select the one that most likely is the problem. Assume CMOS gates. A) A short between the OR gate output and the AND gate input B) A short between the input terminals of the AND gate C) An internal short in the AND gate D) An open connection between the OR gate output and the AND gate input

Trades & Technology