Project reporting, an activity of a project manager, _____.

A. involves the creation of a specific timetable, usually in the form of charts that show tasks, task dependencies, and critical tasks that might delay a project
B. includes informing management, users, and the project team about the progress of a project
C. consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D. includes identifying and arranging project tasks and estimating completion times and costs


Answer: B

Computer Science & Information Technology

You might also like to view...

The ____________________ command removes the selected objects and copies them to the clipboard.     

Fill in the blank(s) with the appropriate word(s).

Computer Science & Information Technology

Most great e-mailers know all of the slang and abbreviations and are encouraged to use them to save time

Indicate whether the statement is true or false

Computer Science & Information Technology

In the accompanying figure, the Passive Sentences percentage is too high; it should not be above ___________ percent.

Fill in the blank(s) with the appropriate word(s).

Computer Science & Information Technology

Which of these expressions:

1. (int)19.00001 2. (int)18.99999 3. (int)19E2 evaluates to 19?

Computer Science & Information Technology