A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's model to determine the aggregated one sigma buffer for this project

Activity Average Worst-Case
A 10 20
B 15 25
C 20 30
D 25 35
A) 20 days
B) 10 days
C) 15 days
D) 5 days


B

Business

You might also like to view...

What characteristics of a location make it appropriate for a press conference? Provide a specific example of a location that benefitted a press conference

What will be an ideal response?

Business

Stockmaster Corporation has provided the following contribution format income statement. Assume that the following information is within the relevant range.   Sales (8,000 units)$320,000Variable expenses 192,000Contribution margin 128,000Fixed expenses 121,600Net operating income$6,400The margin of safety in dollars is closest to:

A. $128,000 B. $121,600 C. $6,400 D. $16,000

Business

In the majority of states, in a case of negligence per se, the plaintiff would only have to prove violation of a statute in order to show negligent conduct

a. True b. False Indicate whether the statement is true or false

Business

American Generation Ecology (AGE) expects to grow at a constant rate of 4 percent forever. Its target debt/asset ratio is 60 percent and it expects to have profitable investments of $300,000 this year. AGE plans to continue paying the same dividend that has been paid the past 20 years, $1.50 per share, long into the future. The firm has 400,000 shares of stock outstanding. If net income is expected to be $800,000, what should be AGE's dividend payout ratio this year?

A. 15.4% B. 25.0% C. 75.0% D. 46.2% E. 60.0%

Business