Use the information in the table and sequence the six jobs using the slack per remaining operation algorithm
Calculate the average flow times and average lateness. All jobs arrived at time zero and are ready at time zero.
Job Production Time Due Date
A 10 20
B 15 25
C 17 22
D 20 31
E 16 20
F 20 24
Job Date Received Prod Time Due Date Slack Slack per operation Order Flow time Late
A 0 10 20 10 3.33 fifth 83 63
B 0 15 25 10 5 sixth 98 73
C 0 17 22 5 1.67 third 53 31
D 0 20 31 11 2.75 fourth 73 42
E 0 16 20 4 1.33 first 16 0
F 0 20 24 4 1.33 second 36 12
TOTAL 98 359 221
AVERAGE 59.83 36.83
Average Flow Time = 59.83
Average Past Due = 36.83
You might also like to view...
Which of the following statements does not correctly describe required income tax disclosures in the notes to the financial statements?
A. The sources that created deferred tax assets and deferred tax liabilities is a required disclosure. B. The statutory tax rate and the effective tax rate are disclosed. C. The expiration date of net operating loss carryforwards must be disclosed. D. The effective tax rate applicable to firms in the same industry is a required disclosure.
The Safe Drinking Water Act (SDWA) sets standards that differ based on the size and usage of the water system.
Answer the following statement true (T) or false (F)
Payroll-related expenses normally are not a material cost to the organization.
Answer the following statement true (T) or false (F)
Achieving ________ in negotiation generally involves making decisions to accept offers, to compromise priorities, to trade off across issues with the other party, or some combination of these elements.
Fill in the blank(s) with the appropriate word(s).