Which of the following best describes project scope?

a. It enables sound economic decisions about whether employees should be assigned to project work or to operational activities.
b. It is the degree to which aproject meets the needs of its users.
c. It ensures that a project meets its essential objectives.
d. It includes all the capital, expenses, and internal cross-charges associated with aproject’s buildings, operation, maintenance, and support.


c. It ensures that a project meets its essential objectives.
Project scope is a definition of which tasks are and which tasks are not included in a project. Project scope is a key determinant of the other project factors and must carefully be defined to ensure that a project meets its essential objectives.

Computer Science & Information Technology

You might also like to view...

Which attribute or behavior would we not factor out of the Pants and Socks classes and into the Clothing base class?

a. material b. color c. isClean d. numberOfPockets

Computer Science & Information Technology

Which location type is used when the computer is connected in an untrusted public location such as an airport?

A. Domain network B. Public network C. Home network D. Work network

Computer Science & Information Technology

How do switches create collision domains? a. Each switch port creates a point-to-point dedicated connection to the devices connected to thatport

b. Switches regenerate each bit of the frames they receive. c. By using a special cable type to connect to the devices on its ports. d. By allowing the interconnection of segments with different speeds.

Computer Science & Information Technology

In programming terminology, a sequence of steps that solves a problem is called an algorithm.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology