Which of the following best describes the critical path of a project?
a. It is the date anentire project should be completed and operational—when the organization can expect to begin to reap the benefits of the project.
b. It identifies the project activities that must be completed, the expected start and end dates, and what resources are assigned to each task.
c. It is a critical date for completing a major part of aproject.
d. It consists of all activities that, if delayed, would delay anentire project.
d. It consists of all activities that, if delayed, would delay anentire project.
The critical path of a project consists of all activities that, if delayed, would delay the entire project. These activities have zero slack time. Any problems with critical path activities will cause problems for the entire project. To ensure that critical path activities are completed on time, project managers use certain approaches and tools such as GanttProject, Microsoft Project, ProjectLibre, or Webplanner to help compute these critical project attributes.
You might also like to view...
Answer the following statements true (T) or false (F)
1. There is only one kind of parameter passing in C++, namely call-by-value. Explain. 2. The call-by-reference mechanism is specified in the function declaration and definition, using a $ between the type and the parameter. 3. The position of the ampersand in the function header is of no importance to the proper compiling and execution of code that uses call-by-reference parameters. 4. A call-by-value parameter may pass data only into a function. 5. A call-by-reference parameter may pass data only out of a function.
A scanner's resolution is measured in _______
Fill in the blank(s) with correct word
To create a custom slide layout, you choose from one of eight different placeholders. _________________________
Answer the following statement true (T) or false (F)
_____ refer to errors, failures, and other computer problems that make computer output incorrect or not useful.
a. Computer-related wastes b. Human errors c. Computer-related mistakes d. Coding errors