Which of the ten knowledge areas defined in the Project Management Body of Knowledge includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully?
a. Project scope management
b. Project quality management
c. Project communications management
d. Project stakeholder management
A
You might also like to view...
A company had revenues of $59,000 and expenses of $46,000 for the accounting period. Dividends of $6500 were paid in cash during the same period. Which of the following entries could not be a closing entry?
A. Debit Income Summary $59,000; credit Revenues $59,000. B. Debit Revenues $59,000; credit Income Summary $59,000. C. Debit Retained earnings $6500; credit Dividends $6500. D. Debit Income Summary $13,000; credit Retained earnings $13,000. E. Debit Income Summary $46,000; credit Expenses $46,000.
Which formula/function in B5 will correctly calculate the expected return of the portfolio?
a) {=SUMPRODUCT(TRANSPOSE(B2:B4),D3:F3)}
b) {=SUM(B2:B4*TRANSPOSE(D3:F3))}
c) =B2*D3+B3*E3+B4*F3
d) =MMULT(H3:J3,F2:F4)
e) All of the above
What is the initial task for employees in an appreciative inquiry process?
a. Identify processes that are causing problems for their organization. b. Identify processes that work well for their organization. c. Envision processes that would work well for their organization. d. Envision future problems or crises that might befall their organization.
Research reports prepared by consultants for their clients tend to be rather formal
Indicate whether the statement is true or false