What is the best way project management can ensure change requests (CR) are appropriately managed?
A. let the team leads handle CRs
B. make sure all CRs are testes
C. put all CR through he normal development methodology
D. create a Change Control Board (CCB)
Answer: D
You might also like to view...
Which of the following statements is true?
a. Performing a task in a program requires a method. b. A method houses the program statements that actually perform its tasks. c. The method hides its statements from its user, just as the accelerator pedal of a car hides from the driver the mechanisms of making the car go faster. d All of the above.
All of the following are basic models for software distribution EXCEPT ________
A) shareware B) freeware C) charityware D) retail software
When a heading is ________, all the sublevels and text associated with the level are hidden
Fill in the blank(s) with correct word
A ________ is a method of incorporating data from multiple, related tables into an Excel worksheet
A) Report tool B) Data Model C) Table tool D) Business Intelligence tool