Given the following chart of jobs assigned with Johnson's rule, suppose that all the jobs (A, B, C, etc) could be evenly divided into two tasks (such as A1 and A2, B1 and B2, etc)
Suppose job B is divided into jobs B1 and B2, each with a body work time of 4.5 hours and a paint time of 2 hours. How much is makespan reduced by this splitting of B?
B1 could start on paint at time = 34.5 (1/2 through the completion of B) but E is busy on paint until t = 35, thus B1 will be delayed until t = 35 to start and thus would finish paint at time = 37. B2 could start on paint at time = 39 and would take until t = 41 to finish. Thus makespan is reduced by 2 hours (43 - 41).
You might also like to view...
Methods used to maintain an audit trail in a computerized environment include all of the following except
a. transaction logs b. transaction listings c. data encryption d. log of automatic transactions
The binomial probability distribution is used with a(n) _____ random variable.
A. continuous B. discrete C. uniform D. intermittent
According to Armstrong and Kotler, what are the five elements of integrated marketing communication? How do organizations employ these elements to achieve their marketing goals?
What will be an ideal response?
Grisham Inc wishes to have an after-tax profit of $400,000. If Grisham's tax rate is 35%, what is their before-tax profit?
A) $615,385 B) $540,000 C) $1,142,857 D) $660,000