The level of the Project Management Maturity Model where there is an organization wide project management system that is tailored to the needs of the organization is called ________ of project management.

Fill in the blank(s) with the appropriate word(s).


institutionalization

In Level 3: Institutionalization of project management, an organization wide project management system, tailored to specific needs of the organization with the flexibility to adapt the process to unique characteristics of the project, is established.

Business

You might also like to view...

Retail stores are often classified on the breadth and depth of their merchandise assortment. The breadth of the merchandise is the number of different lines available. The merchandise breadth may be classified as ________ or ________

A) narrow; broad B) narrow; deep C) shallow; broad D) shallow; deep E) narrow; full

Business

A new machine with a purchase price of $94,000, with transportation costs of $8,000, installation costs of $5,000, and special acquisition fees of $2,000, would have a cost basis of

A) $ 99,000 B) $107,000 C) $102,000 D) $109,000

Business

The random variable x is known to be uniformly distributed between 70 and 100. The probability of x having a value between 80 to 95 is

A. 0.75. B. 0.5. C. 0.05. D. 1.

Business

The purpose of the appropriation of retained earnings is:

a. to allow the corporation to declare higher stock dividends. b. to enable the corporation to pay higher salaries to the board of directors. c. to enable the corporation to pay off outstanding debts. d. to restrict the corporation's right to take over another corporation. e. to restrict the corporation's ability to pay out its assets as dividends.

Business