In the project schedule, the duration of the project is

a. equal to or less than the total of the durations for all the individual activities.
b. more than the total of the durations for all the individual activities.
c. always equal to the total of the durations for all the individual activities.
d. always less than the total of the durations for all the individual activities.


a

Business

You might also like to view...

The marketing data is a repository of a variety of sales-oriented data, some of which result from recording sales events and some of which originate from activities that do not culminate in completed sales, such as presales activities

Indicate whether the statement is true or false

Business

________________ are groups that may be formed based on age, sex, or common interest.

Fill in the blank(s) with the appropriate word(s).

Business

______ is an intervention that makes use of the principle that in everday organizations, we self-organize as we bring new colleagues into conversations, debating ideas, sharing knowledge, challenging thinking, asking questions, and persuading others.

a. World Cafe b. Open Space Technology c. Appreciative Inquiry d. Workout

Business

Apex Insurance Company wrote a large number of property insurance policies in an area where earthquake losses could occur

When the president of Apex was asked if she feared that a severe earthquake might put the company out of business, she responded, "Not a chance. We transferred most of that risk to other insurance companies." An arrangement by which an insurer that initially writes insurance transfers to another insurer part or all of the potential losses associated with such insurance is called A) hedging. B) speculating. C) reinsurance. D) loss avoidance.

Business