A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks

What is the fastest the project can be completed?

Activity Activity time Workers Needed Predecessor
A 10 1
B 4 2
C 7 3 A
D 4 1 A
E 8 2 B
F 9 3 C,E
G 13 1 D
H 14 2 E,G
J 13 3 F
K 10 1 H, J
L 5 2 K
A) 54 days
B) 56 days
C) 58 days
D) 60 days


B

Business

You might also like to view...

When a company declares a 2-for-1 stock split,

a. stockholders' equity is doubled. b. there is no effect on total stockholders' equity. c. a shareholder who previously held 100 shares will have 300 shares after the split. d. the price of each share will be one third of what it was before the stock split.

Business

______ demand social interactions with your company. These consumers constantly use social media to connect with companies, brands, and products.

a. Social Stars. b. Social Savvies. c. Social Snackers. d. Social Skippers. e. None of the above.

Business

Which of the following is not a method for forming a partnership?

A) By agreement B) By estoppel C) By implication D) By transfer

Business

The Sherman Act and Clayton Act (2004) allow prison terms to be imposed on:

a. those involved in burglaries b. those involved in anticompetitive practices c. those involved in blue collar crime d. those involved in drug trafficking e. none of the other choices are correct

Business