Which of the following best describes a gross material requirements plan?

A) a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started
B) an intermediate range plan for the scheduling of families of products
C) a chart illustrating whether capacity has been exceeded
D) a table that corrects scheduled quantities for inventory on hand
E) a schedule showing which products are to be manufactured and in what quantities


A

Business

You might also like to view...

The strength of association is measured by the coefficient of determination

Indicate whether the statement is true or false

Business

Three students were marked as ____ because they did not attend class on the first day

A) no-shows B) nos-show C) nos-shows

Business

Plant assets can be disposed of by discarding, selling, or exchanging them.

Answer the following statement true (T) or false (F)

Business

Eliska is well established as a financial analyst at the Magnify Investment Company. She has significant financial responsibility for her family, and she has recently applied for a mortgage. Which of the following work value categories would likely be important to her?

A. pay B. environment C. achievement D. status E. altruism

Business