In reviewing the budget report of a project, you notice that spending on the project is running about 10 percent over plan. Is the project in trouble? Why or why not?

Fill in the blank(s) with the appropriate word(s).


Answer will vary

You don't know for sure. The project may be in trouble; however the cost overrun could be due to the project being ahead of schedule. You would need to have an earned value analysis run before you could tell.

Business

You might also like to view...

Physical depreciation refers to the loss of usefulness because of inadequacy or obsolescence

a. True b. False Indicate whether the statement is true or false

Business

In the rugby approach to product development, a bottleneck at one phase stops the whole process

Indicate whether the statement is true or false

Business

Reception is the process of ascertaining the meaning and significance of decoded messages for the situation going forward.

Answer the following statement true (T) or false (F)

Business

A nonprofit organization does not hire staff working at a nearby assisted-living facility but does hire staff working at a nearby senior retirement community. This nonprofit organization may be practicing ______.

A. quotas B. merit principles C. disparate impact D. affirmative action

Business