When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?
A. Find the activity with the lowest crash cost
B. Calculate the optimum cost-time point
C. Calculate indirect cost per time unit
D. Calculate the crash point
E. Find the activity with the steepest cost slope
Answer: A
You might also like to view...
Paul DeMairo is identifying key performance indicators to be tracked and analyzed through his company's CRM program. Which of the following would Paul be LEAST likely to include as a key performance indicator?
A) average revenue per customer B) customer lifetime value C) cost to acquire a new customer D) cost to retain a channel member E) cost to retain a current customer
The credit terms 2/10, n/30 are interpreted as:
A. 30% discount if paid within 10 days. B. 30% discount if paid within 2 days. C. 2% cash discount if the amount is paid within 10 days, or the balance due in 30 days. D. 2% discount if paid within 30 days. E. 10% cash discount if the amount is paid within 2 days, or the balance due in 30 days.
In 2002, the following firms except one were awarded the Ig Nobel Prize for the development and application of the concept of “imaginary numbers” that are used in creative accounting in the business world, except
a. Enron b. ExxonMobil c. Arthur Andersen d. WorldCom
Study the following sentence: Social media have created an enormous paradigm shift in what types of stories are considered "breaking news." This sentence would be improved by eliminating a(n) ________
A) buzzword B) flabby expression C) redundancy D) opening filler