Who usually takes primary responsibility for establishing the custom development costs for an SDLC project?
A) end user
B) business manager
C) IS analyst
D) both B and C
C
You might also like to view...
Important issues to consider about team effectiveness include:
A) The structure of the team B) The size of the team C) The life expectancy of the team D) All of the above
As companies experience a shift from labor-intensive operations to automated operations, which of the following costs becomes more difficult to trace to products?
A) Administrative costs B) Direct labor costs C) Direct material costs D) Overhead costs
Using Table 7.4, what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date?
A) one activity B) two activities C) three activities D) four or more activities
Quinton Company has set the following standards for one unit of product: Direct materialQuantity: 6.2 pounds per unitPrice per pound: $11 per poundDirect laborQuantity: 6 hours per unitRate per hour: $23 per hourActual costs incurred in the production of 2,800 units were as follows: Direct material: $194,350 ($11.50 per pound) Direct labor: $393,750 ($22.50 per hour) All materials purchased were consumed during the period.Required: Calculate the direct-material price and quantity variances, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.
What will be an ideal response?