When using the critical ratio (CR) priority sequencing rule:

A) a ratio of less than 1.0 implies that the job is ahead of schedule.
B) a ratio of less than 1.0 implies the job is behind schedule.
C) the job with the earliest due date is scheduled next.
D) the job with the highest CR is scheduled next.


B

Business

You might also like to view...

The shareholders normally determine the price for which shares will be issued unless the charter permits the board of directors to set the price

a. True b. False Indicate whether the statement is true or false

Business

Gremlin Media Inc. has realized tremendous growth in recent years. Last year the firm realized an ROE of 41.16%

If the firm was in a 40% marginal tax bracket, had an asset turnover ratio of 2.1, a profit margin of 14%, and a leverage ratio of 2, what was the firm's retention ratio? A) 0.70 B) 1.00 C) 0.50 D) There is not enough information to answer this question.

Business

Which of the following is TRUE of the long-term forecast?

A) It must go out no further than the next 5 years. B) It can go out as little as 6 months. C) It may be varied to reflect different overall strategic plans. D) It identifies a firm's sales goals and specifies the costs required to meet those goals. E) Its purpose is to show management where it may have cash shortages or surpluses.

Business

With asynchronous transmission, both the parties on a network must be connected at the same time

Indicate whether the statement is true or false

Business