If the most optimistic and pessimistic times for a task are 3 and 11 days respectively, then the variance for the duration of the activity ______.
a. = (3 – 11) / 6) raised to 2
b. = (11 – 3) / 6) raised to 2
c. = (11 – 3) / 3) raised to 2
d. = (3 – 11) / 3) raised to 2
b. = (11 – 3) / 6) raised to 2
You might also like to view...
The financing activities section of the statement of cash flows does not include any transactions or activities from the income statement but does take into account stockholders' equity
Indicate whether the statement is true or false
In new, team based environments, having a group of people who are capable self-leaders is to guarantee the success of a team.
a. necessary and sufficient b. necessary, but not sufficient c. sufficient, but not necessary d. neither necessary nor sufficient
The process of transferring the cost of metal ores and other minerals removed from the earth to an expense account is called
A) depletion B) deferral C) amortization D) depreciation
Use the information in Figure 5.1. What is the throughput time for the A-B-C-E process route?
A) 17 minutes B) 27 minutes C) 21 minutes D) 19 minutes