When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of

A. Doing it twice-first fast and then correctly.
B. Reducing project scope.
C. Compromising quality.
D. Fast-tracking.
E. Using critical-chain project management.


Answer: B

Business

You might also like to view...

The images that we see on television, in advertising, and in movies that have the potential to affect our emotions are known as which of the following?

A. media modes B. media models C. media sets D. media gatekeepers

Business

Which policy reflects the notion that if society enjoys gains that are due to increased efficiency stemming from trade liberalization, some sort of compensation should be provided to those who are temporarily hurt by import competition?

a. countervailing duties b. trade adjustment assistance c. domestic subsidies d. most-favored-nation standard

Business

In order to prepare a sales budget, a ____ is required

A) production budget B) sales forecast C) static budget D) flexible budget

Business

There is (are)_____________judge(s) presiding in a court of original jurisdiction

a. one b. two c. three d. more than three e. between two and five, depending on the case

Business