There are four estimates made for the anticipated cycle time to produce a subcomponent. The estiĀ­mates, in seconds, are 10, 20, 30, and 70. If the first two estimates have equal weights, which total 70%, and the last two are weighted equally with the remaining 30%, what is the expected time?

What will be an ideal response?


E(time) = (0.35)(10 + 20) + 0.15(30 + 70) = 25.5 seconds

Trades & Technology

You might also like to view...

Which vehicles must have low air pressure warning signals

a. Those built after 2010 must have low air pressure warning signals b. Those built after 2005 must have low air pressure warning signals c. All vehicles with air brakes currently in operation must have low air pressure warning signals d. Warning signals are optional

Trades & Technology

The presidential election of 1824

A. was the first to use the electoral college. B. was the first one to see the election of a president who failed to win a majority of the electoral vote from the state electors. C. saw a record high voter turn-out show up at the polls. D. saw the formulation of well-organized political parties. E. was decided by the U.S. Supreme Court.

Trades & Technology

Assistantships with a salary and tuition covered are rarely offered to doctoral students

Indicate whether the statement is true or false

Trades & Technology

Contractors and technicians performing TAB services typically require certification by an independent TAB standards and certification organization such as:

A) UL or CSA. B) NEBB or AABC. C) AHRI or GAMA. D) The EPA or DOE.

Trades & Technology