The milestone schedule in the project charter:
a. is a schedule that provides detailed data for when each project activity should begin.
b. is a detailed schedule that shows the planned duration for every activity in the project.
c. is a summary-level schedule that identifies significant points or events in the project.
d. is a summary-level schedule that shows how major project tasks are sequenced.
C
You might also like to view...
Outsourcing (offshoring)
a. harms the economy’s domestic sectors. b. applies only to manufacturing industries instead of service industries. c. is the transfer of work previously done by domestic workers to workers located in foreign countries. d. refers to the transfer of money capital from domestic banks to foreign banks.
Which of the following types of information is the most important aspect of a marketing research study?
A) basic information B) classification information C) problem-solving information D) identification information E) quantification information
At the beginning of a new project, Edward creates a to-do list for his project team for the entire length of the project, laminates it, and posts it on the wall for all to see. What is wrong with this decision?
a. People from different teams can see the list. b. The to-do list needs to be updated often for new tasks and reprioritization. c. The team was not instructed on what tasks to focus on. d. The to-do list should be sorted based on departmentalization.
Which of the following items that appeared on the bank reconciliation did not require an adjusting entry?
A) bank service charges B) deposits in transit C) NSF checks D) A check for $630, recorded in the check register for $360.