Use the information in the table and sequence the jobs using the EDD rule. What is the average past due?
A) fewer than or equal to 32 hours
B) greater than 32 hours but fewer than or equal to 34 hours
C) greater than 34 hours but fewer than or equal to 36 hours
D) greater than 36 hours
A