A resident project representative should be aware of project safety and if he or she observes a hazardous condition while inspecting the Work, the first thing he or she should do is:
A. ignore the unsafe condition for it is beyond his or her authority.
B. have the unsafe condition repaired on his or her own authority.
C. notify the Building Department of the unsafe condition.
D. inform the general contractor of unsafe condition.
E. order any workers to move out of the hazardous area.
E
You might also like to view...
Which of the following animals provides the most dramatic example of animal communication?
a. Sheep c. Pig b. Horse d. Honeybee
The majority of domesticated dogs are thought to have descended from the Gray wolf.
Answer the following statement true (T) or false (F)
The term quarter-sawed means _____
a) only one-fourth of the tree is used b) the lumber is classified as softwood c) the lumber is cut with the growth rings at an angle greater than 45 degrees d) the log is cut into four equal lengths before it is cut into lumber
The strength of a tapped holes is determined by:
A) The percentage of thread depth cut B) The material being tapped C) The depth of thread engagement D) All of the above