What are the three options an owner has if he chooses to do risk distribution in the contract for construction in regard to subsurface problems?

What will be an ideal response?


Assuming that the owner chooses the risk distribution, the owner has
essentially three options: (1) gather no information, and let the contractor
proceed based on its own evaluation, (2) gather the necessary information,
make it available to the contractor, but disclaim any responsibility for its
accuracy, or (3) gather the information, make it available to the contractor,
and promise the contractor to equitably adjust the contract price if the
actual conditions turn out to differ from those represented or anticipated

Trades & Technology

You might also like to view...

What is the relationship between a WT section and a W-section?

What will be an ideal response?

Trades & Technology

Bison production is decreasing in the United States

Indicate whether the statement is true or false

Trades & Technology

Describe the overhead GMAW welding position.

What will be an ideal response?

Trades & Technology

The process of measuring vertical elevations or distances is called _____

a. uphill leveling b. elevation leveling c. differential leveling d. vertical leveling

Trades & Technology