A critical path activity?

a. Has zero slack time
b. Contributes directly to the duration of the project
c. Has zero slack time and contributes directly to the duration of the project
d. Neither has zero slack time nor contributes directly to the duration of the project


c. Has zero slack time and contributes directly to the duration of the project

Business

You might also like to view...

Cash paid towards salaries is classified in which section of the statement of cash flows?

A) Operating B) Investing C) Financing D) Noncash

Business

Which of the following hierarchical response models assumes the receiver in a persuasive communication situation to be an information processor or problem solver?

A. the hierarchy of effects models B. the five Ws model C. the information processing model D. the AIDA model E. the innovation adoption model

Business

In case of an FLSA violation, employees may file suit to recover back wages and overtime plus liquidated damages:? A) ?for an equal amount

B) ?at half the amount. C) ?at double the amount. D) ?at one-and-half times the amount.

Business

The highest level of control plans are pervasive controls.

Answer the following statement true (T) or false (F)

Business