On the heating plan, a solid line indicates ____ pipes.

A. lead
B. water
C. supply
D. return


Answer: C

Trades & Technology

You might also like to view...

When prospective contractors cannot be relatively certain of what they will be expected to perform, or where they are uncertain as to the techniques needed to accomplish contractual requirements, what type of contract are they likely to prefer?

What will be an ideal response?

Trades & Technology

The development phase includes all of the following except _____.

a. architect/engineers inspecting the project regularly b. producing conceptual drawings c. undertaking land research d. performing feasibility studies

Trades & Technology

What is the common approach to thermostats?

What will be an ideal response?

Trades & Technology

All of the following lines should be drawn thin and dark except:

a. Hidden lines b. Extension lines c. Centerlines d. Phantom lines e. Visible lines

Trades & Technology