Using Table 7.9, if the project's normal earliest completion time is to be reduced by two weeks, what is the minimum additional cost that will be incurred in achieving this two-week reduction?
A) less than or equal to $1,000
B) greater than $1,000 but less than or equal to $1,500
C) greater than $1,500 but less than or equal to $2,000
D) greater than $2,000
B
You might also like to view...
Where litigation in international disputes should occur is
A. dictated by where the problem arose; a problem arising in India is adjudicated in India. B. at times unclear, in which case, the UN International Court of Justice will make a jurisdictional ruling. C. usually evident from the documentation available. D. often complex, so contracts should include choice of law and choice of forum clauses.
The most visible embodiment of total quality management in the United States is
a. being awarded the Deming Prize. b. achieving ISO 9000 certification. c. meeting industry standards. d. recieving the Baldrige Award.
Using Table 7.8, what is the latest start time for activity E?
A) day 7 B) day 8 C) day 9 D) day 10