Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the critical-path algorithm to schedule this project with three processors results in a finishing time of

A. 23 hours.
B. 18 hours.
C. 19 hours.
D. 22 hours.
E. none of these


Answer: B