This resource loading table shows the requirements for a five-task project that has a 42-day duration. The table is designed to reflect an early start schedule. Activity D has only one predecessor and activities C and E have two each
What differences exist between this table and the late start resource table?
The late start table is below. The AC path has slack, so differences arise from the starting times for these activities. Activity A has almost as much slack 8. as its duration 10. as is the case for activity C (duration of 8 and slack of 6). Activity A needs 10 units of resources and C needs 15 units per period, so these resources can be shifted almost the entire duration of either (or both) activities.
You might also like to view...
Choose the correct word or words in parentheses. Ms. Ramirez arranged a training session for him and (I, me)
Orson was fired from his job behind the ticket counter at the airport. He was loudly told to put his personal belongings into a plastic bag and was led out by security guards in front of his co-workers and customers. His supervisor told him not to return. Orson's employer faces potential liability for:
a. intentional infliction of emotional distress. b. whistleblowing. c. defamation. d. violation of the FLSA.
Under the Second Restatement, the duty of a possessor of land to persons who come on the land usually depends on whether those persons are:
a. invitees, trespassers, or licensees. b. reasonable persons. c. fiduciaries. d. involved in abnormally dangerous activities.
Efforts to change a brand's focus to target new markets or change the image of a brand are called
A. co-branding. B. brand collusion. C. brand dilution. D. brand repositioning. E. brand extraction.