Risk in a revenue-producing project can best be adjusted for by:?
A. ?ignoring it.
B. ?adjusting the discount rate upward for increasing risk.
C. ?adjusting the discount rate downward for increasing risk.
D. ?Picking a risk factor equal to the average discount rate.
E. ?reducing the NPV by 10 percent for risky projects.
Answer: B
You might also like to view...
Run-to-run control totals can be used for all of the following except
a. to ensure that all data input is validated b. to ensure that only transactions of a similar type are being processed c. to ensure the records are in sequence and are not missing d. to ensure that no transaction is omitted
If rewards are distributed based on personal performance levels, a perception of ______ can be created if managers don’t make clear why some are provided with greater incentives than others.
A. fairness B. merit C. variableness D. favoritism
In addition to the above-mentioned explicit questions for the future, can you identify other important questions which Farggi managers should consider in early 1995?
What will be an ideal response?
Which form of tracking is exemplified by counting the number of pieces of content uploaded to a microsite after the fact?
a. Reverse. b. Forward. c. Opportunity. d. Coincident. e. Baseline.