List the factors that apply when determining the necessary time frame for approval of submittals.

What will be an ideal response?


Some factors that apply when determining the necessary time frame for approvals include the following:

1. The size of the submittal package to be submitted. If a submittal is divided into packages, the approval time would be less per package than it would be for the entire submittal.

2. The complexity of the submittal has a large influence on the review and approval time.

3. The timing of the submittal. If all of the project submittals are given to the architect on the same date, it would take considerable time to process the submittal.

4. The number of consultants reviewing the submittal will influence the processing time. Occasionally, several consultants will review the submittal, which requires additional time for reviewing, handling, and mailing.

5. Some of the architect's consultants may live in other geographical areas; thus, mailing time should be considered in the approval process.

Trades & Technology

You might also like to view...

A ____ should be used for cleaning the sole, frog, and hoof wall.

A. hoof pick B. dandy brush C. curry comb D. finishing brush

Trades & Technology

Name three explant types used to regenerate diploid plantlets from adventitious shoots.

What will be an ideal response?

Trades & Technology

Find the volumetric efficiency of a 1.8L engine operating at 6000 RPM. The actual airflow through the engine is 171.0 CFM. Round your result to the nearest percent

What will be an ideal response?

Trades & Technology

Which type of oscilloscope displays all voltages without taking samples?

A) Digital B) Complex C) Analog D) None of these

Trades & Technology