Which of the following improper operation is least likely to extend start-up time and increase start-up cost?
A) Tower not vented
B) No cooling liquid on condenser
C) Opening a bleed valve on a positive pressure column
D) Introduction of steam to reboiler during startup
Answer: C
Explanation: A) Incorrect. Tower not vented is likely to extend start-up time and increase start-up cost.
B) Incorrect. No cooling liquid on condenser is likely to extend start-up time and increase start-up cost.
C) Correct. Opening a bleed valve on a positive pressure column is least likely to extend start-up time and increase start-up cost.
D) Incorrect. Introduction of steam to reboiler during startup is likely to extend start-up time and increase start-up cost.
You might also like to view...
What would the shaft and hole size be for a Ø.50 nominal size using an RC4 fit?
a. shaft ø.4870/.4094, hole ø.5000/.5100 b. shaft ø.4987/.4994, hole ø.5000/.50001 c. shaft ø.4987/.4994, hole ø.5000/.5100 d. shaft ø.4987/.4994, hole ø.5000/.5010
The name used for stone that has been cut or cleaved
What will be an ideal response?
When servicing an air bag, which of these is the first step taken?
A) Disconnect the clockspring electrical connector B) Disconnect the battery negative cable C) Disconnect the impact sensors D) Take resistance measurements at all electrical connectors
A carbon steel ring, with a piece of soft metal bolted across the middle of the ring is a _____
a. steam target b. test tree c. slip blind d. blind flange