Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the priority list, C, E, G, F, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
A. 21 hours.
B. 24 hours.
C. 22 hours.
D. 26 hours.
E. none of these
Answer: D