Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the priority list, C, E, G, F, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of

A. 21 hours.
B. 24 hours.
C. 22 hours.
D. 26 hours.
E. none of these


Answer: D

Mathematics

You might also like to view...

Solve each equation for y as an expression in x. Then equate the expressions to obtain an equation in the variable x. Finally, solve the equation for the unknown x.y - 37x = -36; y - 7x = 9

A.
B.
C.
D.

Mathematics

Solve the problem.For f(x) = 9 - 2 and g(x) = 5 + 4. Find an equation for f - g.

What will be an ideal response?

Mathematics

Find the vertex, focus, and directrix fo the parabola.

Mathematics

Shade the portion of the diagram that represents the given set.(A ? B) ? 

A.

B.

Mathematics