If the most optimistic and pessimistic times for a task are 3 and 15 days respectively, then the variance for the duration of the activity is ______.

a. 3.00
b. 4.00
c. 5.00
d. 6.00


b. 4.00

Business

You might also like to view...

You are the CEO of a multi-billion dollar company. Your company employs over 75,000 people. The company is being sued for $100 million dollars as the result of racial discrimination against your customers. Your investigation reveals that some of your

managers are actively violating the law. Discuss the steps you would take to ensure your company's compliance with ethical norms and legal requirements.

Business

Tarletto Inc.'s current year income statement includes a $229,000 gain realized on the exchange of an old business asset for a new business asset. If the exchange is nontaxable, Tarletto's book basis in the new asset is $229,000 greater than its tax basis.

Answer the following statement true (T) or false (F)

Business

The supply chain is a network of manufacturers and service providers that work together to create products or services needed by end users

Indicate whether the statement is true or false.

Business

Lincoln Lodging Inc. estimates that if its sales increase 10.00% then its net income will increase 15.00%. The company's EBIT equals $2.4 million, and its interest expense is $400,000. The company's operating costs include fixed and variable costs. What is the level of the company's fixed operating costs? Do not round your intermediate calculations.

A. $720,000 B. $558,000 C. $624,000 D. $600,000 E. $534,000

Business