The project described by:
Activity Immediate
Predecessor Time
(days)
A -- 6
B A 2
C -- 8
D B, C 5
E D 7
has a critical path of length of
A) 15 days.
B) 20 days.
C) 17 days.
D) 18 days.
E) None of the above
B
You might also like to view...
Key words that match the job description should be included in the résumé because
a. it shows you were paying attention. b. scanning programs can detect the words and match the language. c. your résumé will look more specific. d. they eliminate too much white space.
Why do stores cluster together?
A) to decrease competition B) to ensure an adequate level of traffic C) to take advantage of tax breaks D) to create retailer cooperatives E) to standardize the service mix
Use the following data to find the direct labor efficiency variance if the company produced 3,500 units during the period. Direct labor standard (4 hrs. @ $12/hr.)$48per unitActual hours worked 12,250 Actual rate per hour$12.50
A. $7,000 unfavorable. B. $7,000 favorable. C. $21,000 favorable. D. $6,125 favorable. E. $6,125 unfavorable.
The first action generally attempted by the EEOC is: A) litigation
B) conciliation. C) mediation. D) arbitration.