A project consists of seven independent tasks with processing times (in hours) given by 3, 4, 4, 5, 7, 7, and 11.Find the finishing time Fin for N = 3 processors using the critical-path algorithm.

A. Fin = 12 hours
B. Fin = 16 hours
C. Fin = 15 hours
D. Fin = 11 hours
E. Fin = 14 hours


Answer: C

Mathematics

You might also like to view...

Choose the graph that matches the function. f(x) = 5x + 6

A.

B.

C.

D.

Mathematics

Find the most general antiderivative.dt

A. t3/2 - t8/7 + C
B. t1/2 - t-6/7 + C
C.  -  + C
D. t3/2 - t8/7 + C

Mathematics

Use the brute force algorithm to find a minimum Hamilton circuit for the graph. Also, determine the total weight of the minimum Hamilton circuit.

A. Minimum Hamilton circuit is W ? Y ? X ? Z ? W; weight = 17 B. Minimum Hamilton circuit is W ? Y ? X ? Z ? W; weight = 22 C. Minimum Hamilton circuit is W ? X ? Y ? Z ? W; weight = 19 D. Minimum Hamilton circuit is W ? X ? Z ? Y ? W; weight = 16

Mathematics

List the terms of the expression.4x3 + 5x2 - 3x + 6

A. 4x3, 5x2, -3x, 6 B. 4, x3, 5, x2, -3, x, 6 C. 4x3, 5x2, 3x, 6 D. 4x3 + 5x2, -3x + 6

Mathematics