A project consists of seven independent tasks with processing times (in hours) given by 3, 4, 4, 5, 7, 7, and 11.Find the finishing time Fin for N = 3 processors using the critical-path algorithm.
A. Fin = 12 hours
B. Fin = 16 hours
C. Fin = 15 hours
D. Fin = 11 hours
E. Fin = 14 hours
Answer: C
You might also like to view...
Choose the graph that matches the function. f(x) = 5x + 6
A.
B.
C.
D.
Find the most general antiderivative.dt
A. t3/2 -
t8/7 + C
B. t1/2 -
t-6/7 + C
C. -
+ C
D. t3/2 -
t8/7 + C
Use the brute force algorithm to find a minimum Hamilton circuit for the graph. Also, determine the total weight of the minimum Hamilton circuit.
A. Minimum Hamilton circuit is W ? Y ? X ? Z ? W; weight = 17 B. Minimum Hamilton circuit is W ? Y ? X ? Z ? W; weight = 22 C. Minimum Hamilton circuit is W ? X ? Y ? Z ? W; weight = 19 D. Minimum Hamilton circuit is W ? X ? Z ? Y ? W; weight = 16
List the terms of the expression.4x3 + 5x2 - 3x + 6
A. 4x3, 5x2, -3x, 6 B. 4, x3, 5, x2, -3, x, 6 C. 4x3, 5x2, 3x, 6 D. 4x3 + 5x2, -3x + 6