Quality Builders contracted to build Shawn a home according to specifications. Payment was to be made monthly for work completed the previous month. Shawn missed a payment and Quality stopped working. Quality sued Shawn for breach of contract seeking the missed payment.?
A. Shawn's "no breach, justification" response was based on Quality's material breach.
B. ?Shawn's "no breach, justification" response was based on Quality's lack of substantial performance.
C. ?Shawn's "no breach, justification" response was based on Quality's failure to comply with the contract.
D. ?Shawn does not have a "no breach, justification" response.
Answer: B
You might also like to view...
What kind of signature needs to be in your office e-mail?
A. Just your formal signature is satisfactory. B. A confidentiality statement is necessary. C. Contact information is necessary. D. Your identification as a legal assistant or paralegal is necessary. E. None of the above F. Just your formal signature is satisfactory, and a confidentiality statement and contact information are necessary.
Judgment
What will be an ideal response?
In regard to counteranalysis:
A. There may be situations in which counteranalysis is not necessary B. Analysis is not complete unless there is counteranalysis C. Rebuttal is always required when there is counteranalysis D. There may be situations in which rebuttal is not required E. Answers a and d above F. Answers b and c above G. Answers b and d above
An oral deed is enforceable.
Answer the following statement true (T) or false (F)