Your firm has expertise with a special type of hand-finished furniture. The learning curve is known to be 82%. If the first piece of furniture took 6 hours, estimate (using the doubling approach) how long it will take to complete the third unit

What will be an ideal response?


Using the doubling approach, the second unit will take 0.82 ? 6 = 4.92 hours and the fourth unit will take 0.82 ? 0.82 ? 6 = 4.03 hours. The third unit must take an amount of labor between these two values, but not exactly halfway. There is more absolute improvement from unit 2 to unit 3 than from unit 3 to unit 4. A reasonable estimate would be about 4.4 or 4.5 hours (the answer from Excel OM is 4.38 hours).

Business

You might also like to view...

Who among the following are exempt from child labor restrictions in the United States?

A) children who work as newspaper deliverers B) children who work at restaurants or fast-food stalls C) children employed in the performing arts D) children employed in gasoline stations

Business

According to ______ theory, specific difficult (but achievable) goals consistently lead to better performance than specific easy goals, general (do your best) goals, or no goals.

A. work goal B. goal-setting C. expectancy D. content

Business

Several art distributors have met and agreed to limit the number of Hummel figurines being imported into the United States. Is there any anticompetitive behavior involved in doing this?

Business

If you roll a 6-sided die, what is the probability that it will land on 6?

a. 1/6 b. 2/6 c. 6 d. none of the above

Business