The overall project risk factor is known to be 0.6. The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure

The consequence of performance failure is twice the consequence of reliability failure, four times the consequence of schedule failure and eight times the consequence of cost failure. What is the probability of maturity failure?

Maturity X Cost Y
Complexity 2X Schedule 2Y
Dependency 4X Reliability 4Y
Performance 8Y
A) 0.213
B) 0.197
C) 0.104
D) 0.148


D

Business

You might also like to view...

An employee with an EB-1 visa cannot apply for U.S. citizenship

Indicate whether the statement is true or false

Business

What type of control chart monitors the percent defective in a sample?

a. P b. C c. x-bar d. R

Business

If a firm takes on ________ it may be downgraded by rating agencies, resulting in ________ interest payments

A) too much incremental debt; lower B) too much incremental debt; higher C) too little incremental debt; lower D) too little incremental debt; higher

Business

________ of procurement officers use auctions to purchase goods

A) 80% B) Less than a quarter C) Over one third D) 25%

Business