What are some of the reasons that projects dates and costs get off track? How can a baseline on a current project help with future planning?

What will be an ideal response?


Some of the reasons project dates and cost get off track include the original plan not being accurate or no longer being accurate because the scope of the project has crept or because the nature of the project has changed. Other possible reasons for changes in the original plan include weather-related delays, labor issues, or personal problems such as missed time with specific resources. Baseline information that consistently differs from current data provides you with variance information so that you can plan better for future projects with better estimates for costs and dates.

Computer Science & Information Technology

You might also like to view...

Is captioning an effective assistive strategy for everyone who has a hearing impairment? Justify your answer.

What will be an ideal response?

Computer Science & Information Technology

Communication systems that rely on start and stop flags or bits to manage data transmission are known as what type of communication?

A. Analog B. Digital C. Synchronous D. Asynchronous

Computer Science & Information Technology

Describe the differences between a brownout and a blackout.?

What will be an ideal response?

Computer Science & Information Technology

The adjacency matrix uses a vector for the vertices and a matrix to store the edges.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology